Schedule of Works
(works carried out by December 30, 2013)
Includes the installation of 2349 solar systems for residential buildings within the Suski Poviat and a single solar system for the local hospital in Sucha Beskidzka
a) System installation order
On 16 February 2012 the communes where the solar systems were to be installed were randomly picked in the presence of mayors, the Poviat Board and the Environment Commission.
Films from this event can be seen here
The order is as follows (number of systems in the brackets ) :
1. Maków Podhalański (391)
2. The town of Jordanów (176)
3. Sucha Beskidzka (313)
4. Stryszawa (493)
5. Zembrzyce (151)
6. Budzów (226)
7. The commune of Jordanów (252)
8. Bystra-Sidzina (112)
9. Zawoja (235)
b) Deadline for the installation of the solar systems for residential buildings – 31 August 2013 r.
c) Deadlines for the installation of the solar systems in individual communes :
Ref |
Commune |
Commencement of works |
Completion of works |
1 |
Maków Podhalański |
07-08-2012 |
9-10-2012 |
2 |
Miasto Jordanów |
10-10-2012 |
26-10-2012 |
3 |
Sucha Beskidzka |
26-10-2012 |
6-12-2012 |
4 |
Stryszawa |
20-11-2012 |
11-04-2013 |
5 |
Zembrzyce |
11-04-2013 |
07-05-2013 |
6 |
Budzów |
07-05-2013 |
11-06-2013 |
7 |
Gmina Jordanów |
11-06-2013 |
12-07-2013 |
8 |
Bystra-Sidzina |
12-07-2013 |
26-07-2013 |
9 |
Zawoja |
26-07-2013 |
31-08-2013 |
d) Deadlines for the installation of the solar systems in individual properties:
Schedule > Communes> Select commune (please, look below)
e) Deadline for the installation of the solar system for the local hospital - 31 December 2012
PLEASE NOTE : Schedules, including crew numbers, may change because of the causes independent of the Contractor or the poviat (e.g. weather conditions, no contact with residents, building alteration, etc.).
The Contractor will contact the residents by phone before the commencement of works.
Because of the project size and the task complexity, we ask for your patience and understanding.